PLM training · Part 2 / 8

Season calendar and line plan

Audio narration · listen first

A collection runs on a calendar built backward from the launch date. The line plan says how many styles will come out in each category; the calendar says which stage each style must be at on which date.

In this part

  • You understand how the calendar is built backward from the launch date.
  • You put the design, sample, approval, production and shipment milestones in order.
  • You see what the critical path is and how one delay shifts the launch.
  • You explain how the line plan and the calendar feed each other.
Season calendar and line plan: Pimland PLM screen
Season and collection calendar: every milestone is shown with its planned date. A step at risk of delay is spotted before the launch.

Terms in this part

Season (SS/AW)
Grouping collections by selling period: Spring/Summer (SS) and Autumn/Winter (AW).
Line plan
The collection plan showing, for each category of a season, how many styles, which price band, how many colors and what quantity will go out.
Delivery date
The date by which a task, material or order must be delivered.
Critical path
A chain of linked tasks where any delay directly pushes back the launch.
Drop
Releasing a collection for sale in parts on set dates, rather than all at once.
← Previous part

There are 3 questions at the end of the part; at least 2 correct answers open the next part. The questions open with your Academy account, after your Basic certificate.